The Simmons Project Timeline
Left Coast Pool Concepts, Inc.
Debbie & Chris Simmons of La Quinta hired LCPC on 03-19-2007 to oversee
& manage their new swimming pool project. We designed the pool,
submitted to the HOA for approval and received our city construction permit
within 10 days. On 4-3, we laid out the pool in the backyard and had the
entire pool excavated by that evening. The following morning, on 4-4, we
installed the steel reinforcement and completely plumbed the pool that same
afternoon. I called the project in for a pre-gunite inspection which passed
100% on 4-5. Gunite was shot & completed on 4-9 and the equipment and
electrical was connected on 4-10. On 4-11, Mrs. Simmons & I went to select
pool tile & grout. On 4-12, we began the grading of the yard & setting the
forms for the deck. This continued through 4-13 and the deck was poured,
scored and salt finished on Saturday, 4-14. On 4-17, the tile was installed and
the pre-plaster inspection passed on 4-20. The pool was plastered on 4-25
and filled with water. The start-up service began on 4-26.
22 days to build a pool from excavation to filling it with water!


Mario M. Horvath
Layout on 4-3-07
Excavation on 4-3-07
The Simmons children w/ neighbor in
excavated pool - 4-3-07
Steel reinforcement - Morning of 4-4-07
Plumbing - Afternoon of 4-4-07
Plumbing completed 4-4-07
Left Coast Pool Concepts
The smart and affordable
choice
You need Java to see this applet.
Gunite application 4-9-07
Equipment set, salt chlorinator
& electrical system complete on
Setting the forms 4-12-07
Pouring the Decking 4-14-07
Tile installed 4-17-07
Pool plastered 4-25-07